VESI · Official form

EWR: Electrical Work Request

The Electrical Work Request (EWR) is the standard form a registered electrical contractor uses to ask a Victorian electricity distributor to connect, alter or disconnect a supply. Fill in the official PDF below and download it.

This is the genuine VESI PDF, unmodified. Source: VESI official page.

What is EWR?

The EWR is published under the Victorian Service and Installation Rules (VESI), the technical rules that govern how customer installations connect to the distribution network in Victoria. It is the single request form the five Victorian distributors accept, so the same document works whether the network is CitiPower, Powercor, AusNet Services, United Energy or Jemena. The contractor uses it to notify the distributor of electrical work and to request the network activity that goes with it.

One EWR can cover a new connection, a supply upgrade or phase change, a metering request, a temporary builders supply, an asset relocation, or an abolishment where the supply is removed. It records the site address and NMI, the customer details, the installation particulars such as mains size and phases, and the registered electrical contractor licence details. Because it is a normal fillable PDF rather than a dynamic Adobe form, you can complete it here in your browser.

Who files EWR?

  • Registered electrical contractors arranging a new or altered connection in Victoria
  • Contractors requesting metering work, a phase change or a supply upgrade
  • Contractors arranging a temporary builders supply for a construction site
  • Contractors requesting an abolishment or relocation of an existing supply

How to fill out EWR

  1. Enter the site address and the National Metering Identifier (NMI) for the premises, along with the customer or retailer details.
  2. Choose the type of work requested, such as a new connection, supply alteration, metering, temporary supply or abolishment.
  3. Fill in the installation particulars: the number of phases, the mains and service cable size, the main switch rating and any load details the distributor needs.
  4. Add your registered electrical contractor number and licence details, then sign and date the declaration.
  5. Send the completed EWR to the electricity distributor that services the site, following that distributor’s current lodgement process.
Worth knowing: The EWR is completed by a registered electrical contractor, not by the property owner. Lodgement channels differ between the Victorian distributors, so confirm the current process with the distributor that services the site.

Quick fill EWR on this page

Prefer to see the form itself while you type? Open EWR in the editor to fill it on the actual pages, add a signature, and download.

These are the form's own fields, in the order they appear on the pages. Fill in what you know; anything left blank stays a fillable field in the PDF, so you can finish it in any PDF reader. Nothing you type here is sent to VESI.

Page 1 106 fields

Processed on our own servers, never sent to a third-party service. Files are deleted automatically after two hours, and you can delete them sooner from the result screen.

Frequently asked questions

Who can lodge an EWR?

The EWR is a contractor document. A registered electrical contractor completes and lodges it with the distributor. Property owners arrange the work through their contractor and their electricity retailer rather than lodging the form themselves.

Which distributor do I send it to?

Send it to the network that services the site address, which is one of CitiPower, Powercor, AusNet Services, United Energy or Jemena in Victoria. Each distributor sets its own lodgement channel, so check the current process on the distributor’s website.

Is the EWR the same as a certificate of electrical safety?

No. The EWR requests network work from the distributor. A Certificate of Electrical Safety is a separate document lodged with Energy Safe Victoria to certify that the electrical work itself is safe and compliant.